23 July 2025 KRZYSZTOF BRYSIEWICZ

Refunds – common sense or rigour? The Supreme Court responds

Today, the justification of the judgment I CSK 878/14, to which I referred in my previous post, was published on the Supreme Court’s website. This is probably one of the most important judgments in cases concerning European funds that have been made in recent years, so below I will briefly take the liberty to comment on the key theses presented in the justification.

As a reminder, the case concerned the beneficiary’s failure to achieve one of the goals of the project, i.e. an increase in employment, which was the direct cause of termination of the funding agreement and the institution’s pursuit of full reimbursement. The beneficiary undertook to increase employment by 27 new jobs in relation to the existing 453 jobs. The Supreme Court found the findings of the institutions and the lower courts to be correct insofar as they concerned the lack of an increase in employment and concluded that, indeed, the beneficiary had not increased employment.
The creation of new jobs was one of the important objectives of the project and, as the course of the evidence shows, without the commitment to increase employment beyond the 453 people already employed shown in the application for funding, the defendant’s application would not have been accepted for implementation.

Zwrot co najwyżej proporcjonalny…

However, in the opinion of the Supreme Court, the mere failure to achieve this goal did not justify the withdrawal of the entire subsidy, as the project also envisaged the implementation of other goals, which were achieved by the beneficiary.
However, the allegations of the cassation complaint, in which it is claimed that, despite the material side of the investment having been realised, i.e. the purchase and implementation of the production of the modern heating device, which was accepted by the conducted inspections, the defendant is required to return the entirety of the aid granted, also in this properly realised scope. The applicant’s doubts must be shared and it must be acknowledged that the purpose of the aid to which the provision of financial support from EU funds relates cannot be reduced to the result of an increase in employment alone if, moreover, the question of employment was not the sole reason for concluding the agreement on the provision of financial support, but was, on account of the subject-matter of the funding, an important but additional problem. ”

The defendant should not be imputed the obligation to return the entire amount of the support provided just because it did not implement the project in its entirety, claiming that this occurred contrary to the actual purpose of the contract and that it used the funds provided to it contrary to the contract for the implementation of the project, i.e. contrary to their purpose. The cited findings point to a different conclusion, i.e. that the basic purpose of the agreement was fulfilled and it would be profoundly unfair to interpret the provisions of the European Union law and the provisions of the Polish law harmonised with them, as well as the ratio legis of the solutions contained therein, in such a way as to drastically burden the respondent Company with the obligation to return the entire subsidy, i.e. also that part of it which was effectively for the economy and correctly used.

... and once the reasons for not achieving the purpose of the contract have been establishe

Importantly also, according to the Supreme Court, the question of the reasons for the beneficiary’s failure to maintain the existing employment was not irrelevant. In this regard, in the court’s view, the beneficiary could only be held responsible for the failure to achieve the objectives of the contract for reasons attributable to the beneficiary.

The view must therefore be favoured that, if the defendant should repay the financial assistance received, it should be for that part, ring-fenced from the outset, which was allocated to the increase in employment and to the extent that it failed to comply with its obligation for reasons attributable to it

Therefore, in the opinion of the Supreme Court, the Court of Appeal, when reviewing the case, should examine why the employment was not maintained at the indicated level and whether the employees who were to be hired under the project were subject to redundancies that affected the company globally or whether they were still employed at the date of the beneficiary’s audit.

Many factors affecting employment cannot be predicted at the time of contracting for future years. If economic considerations and rationalisation of the workforce resulted in the defendant employing only 311 of the 453 employees at the time of the application at the time of the audit, which questioned the validity of the assistance provided, then arguably that contractual objective of increasing the workforce had not been achieved. However, it is not shown in the reasons of the Court of Second Instance whether the employees who were still employed by the defendant include those who were taken on as part of the increase in employment of 27 persons. Although the defendant's explanation for not retaining the employment of the increased number of 27 employees is that they were only to be employed for the duration of the project, which is an erroneous and ineffective explanation, it may be that these very employees or a certain group of them were still employed at the time of the inspection and that the reduction concerned other persons and was not related to the implemented project which was the subject of the grant.

Common sense prevail

The view presented in the justification for the judgment under comment, which is in a way an emanation of views already presented earlier in the case law of common courts and the Supreme Court, deserves, in my opinion, full approval. I have already pointed out on several occasions that the objectives of a funding agreement also have a certain weight on the public side. Therefore, if a beneficiary contributed to the implementation of strategic objectives of a given programme/measure (e.g. built a scientific and research centre, introduced an innovative solution, commercialised an invention) – it is difficult to speak of withdrawing the entire co-financing, even if there were some failures in the project. Thus, in answering the title question, the Supreme Court unequivocally opted for the criterion of common sense when assessing claims for reimbursement of funding. This is all the more important as such a common sense assessment is also anchored in EU regulations (which I will be mentioning in more detail in the near future). In conclusion, it basically remains for me to give the floor to the Supreme Court again:

Claiming repayment of funds also in the part used correctly, which was not at all contested in the case against the respondent, cannot be served by a strict view of the relevant EU regulations (including Commission Regulation (EC) No 1681/94 of 11 July 1994. on irregularities and the repayment of sums wrongly paid in connection with the financing of structural policies and the organisation of information systems in this field), if that not only fails to comply with the provisions of Polish law in relations between the State Treasury and the contracting party as regards the obligation to repay the funds, but also breaches the principles of rational economy and reasonable spending of aid funds and, moreover, harms the entrepreneur who is the addressee of the aid, which was used correctly in its essential amount.

About author

Autor
Ask the author a question KRZYSZTOF BRYSIEWICZ Managing Partner / Legal Counsel
I specialize in handling cases related to state aid and EU funds. I enjoy challenges, which is why I willingly represent clients in difficult and complex matters. I am also eager to share my knowledge at industry and academic conferences, as well as through blog articles.

Contact for media

Avatar
Katarzyna Jakubowska PR Manager

Newsletter

Bądź na bieżąco. Otrzymuj informacje o nowych publikacjach ekspertów z Kancelarii Brysiewicz, Bokina, Sakławski i Wspólnicy

[FM_form id="1"]